This winter, two large road projects will begin. The City started working in 2022 on the design and coordination for 200 North between Main Street and Fruit Heights to replace underground water and sewer lines, fire hydrants, and water services, as well as to install missing curb and sidewalk, finishing with a repave of 200 North. This multi-year project will soon start at Main Street and make its way east. Depending on weather and underground conditions, this project could take two years to complete.
Another project starting this winter is the installation of a traffic signal at Mutton Hollow and Main Street. This will involve a significant amount of new curb installation and widening the southbound lanes of Main Street to two lanes. At a later date, another project will be undertaken to install a traffic signal at Mutton Hollow Road and Fairfield Road.